East Village Revitalization



									

							
			
			
			
			
			
        
                                                                                
					                        
    
                                                                                					                                        					
																																			
                                                    
					                                            
            

The East Village Revitalisation project is transforming a neglected, uninviting region in Qualicum Beach’s uptown area which is framed by Memorial Avenue and bordered by Fir Street, Fern Road and Berwick Road. The project will create a unique and thriving neighbourhood for both businesses and residents.

Key components of the revitalization include:

  • Adding public spaces, including a community gathering area with a stage.
  • Re-configuring and repaving the streets to emphasize pedestrians and a focus on accessibility.
  • Activating the public realm by adding street trees, new lighting, public seating areas and planters.
  • Creating linkages between East Village and uptown through the use of laneways and trails.
  • Engaging town-owned land to foster creative uses such as an innovation hub and brewpub.

So far Berwick Road (Phase 1) and Second Avenue (Phase 2) have been revitalized, and work is anticipated to continue along Fir Street (Phase 3) to create a fully restored neighbourhood.

East Village Opens (19)
Empty road running alongide brown brick sidewalk, with a sapling tree in the foreground and a fire hydrant and lamppost in the background.
East Village Opens (5)
Silvacell3
East Village (5)
Carved Bench_2
20211005_124618
Silvacell3
East Village Opens (19)
Empty road running alongide brown brick sidewalk, with a sapling tree in the foreground and a fire hydrant and lamppost in the background.
East Village Opens (5)
Silvacell3
East Village (5)
Carved Bench_2
20211005_124618
Silvacell3

Phase 1 (Berwick Rd)

  • 2018 – East Village Policies adopted in Official Community Plan
  • 2019 – Design approved by Council
  • Fall 2019 – Brew pub constructed
  • Winter 2019 – Provincial funding received
  • 2020 – ICET funding received
  • Summer 2021 – Spring 2022 – Construction Phase 1

Phase 2 (Second Ave)

  • Sept 2022 – Development Permit approved
  • Nov 2022 – Construction Phase 2
  • Aug 2023 – Phase 2 Completes

Phase 3 (Fir Ave)

Phase 3 is anticipated to continue along Fir Street to create a fully restored neighbourhood.

Phase 2 – 2022

Phase 1 – 2020

To contact the Town with questions or inquiries related to this project please use the Public Inquiry Form.

Public Inquiry Form