Little Qualicum River Erosion Protection



									

							
			
			
			
			
			
        
                                                                                
					                        
    
                                                                                					                                        					
																																								
					

					
                                                    
					                                            
            

The project will involve the construction of instream erosion protection works to reduce river flow velocities and stabilize the riverbank adjacent to the Town’s River Wellfield, which supplies approximately 90 per cent of the community’s potable water. The project will also include habitat enhancement features to support fish and environmental health.

The project was developed with support from hydrotechnical engineers, environmental professionals, and regulatory agencies, including Fisheries and Oceans Canada, and includes ongoing engagement with Qualicum First Nation.

  • May 2026  – Tender issued for construction
  • May 2026  – Tender issued for project management
  • Summer 2026 – Work to commence
  • Fall 2026 – Work to complete
  • Implementation Work – $843,700 from the Province’s Disaster Resilience and Innovation Funding (DRIF) program.
  • Design Work – $125,000, through the Union of BC Municipalities’ – Disaster Risk Mitigation and Climate Adaptation program.

To contact the Town with questions or inquiries related to this project, please use the Public Inquiry Form.